Case Studies

See how Nichi New Energy systems cut costs and improve reliability in real Nigerian operating conditions.

Lagos manufacturing rooftop
500 kW PV + 1 MWh ESS

Lagos Manufacturing Plant

System: 500 kW solar PV + 1 MWh lithium battery storage + existing diesel backup

Challenge: Daily grid outages of 6–10 hours forced the plant to run diesel generators for most of the day, driving up production costs.

  • Diesel runtime reduced by 72%
  • Annual fuel savings estimated at ₦45 million
  • Payback period under 5 years
  • Improved production uptime and power quality
Abuja residential estate
50 × 10 kWh home systems

Abuja Residential Estate

System: 50 sets of 10 kWh residential ESS + 5 kW hybrid inverters + rooftop PV

Challenge: Estate residents relied on shared diesel generators with noisy operation, variable billing and frequent downtime.

  • 24/7 power for essential loads
  • Generator use limited to long rainy spells
  • Transparent per-unit energy monitoring
  • Residents report 40% lower monthly energy spend
Northern Nigeria telecom tower
15 kW solar + 60 kWh battery

Telecom Tower Site

System: 15 kW DC solar + 60 kWh LFP battery + smart diesel controller

Challenge: Remote location with expensive and risky diesel logistics. Site ran DG 18–20 hours per day.

  • DG runtime reduced to 4 hours/day
  • Fuel delivery trips cut from weekly to monthly
  • Battery + solar handles daytime base load
  • Fast deployment with minimal civil works

Typical Project ROI

Based on Nigerian diesel and grid-tariff assumptions for C&I clients.

📉

30–60%

Diesel cost reduction depending on solar fraction and battery size

4–7 Years

Typical payback period for C&I solar + storage systems

🔋

6,000+ Cycles

LFP battery cycle life with 10-year product warranty options